By Phillip Mancini, registered building practitioner · Last updated 24 October 2026

The Beaumaris Project is two double-storey dwellings on a corner site that I designed as my own development. It needed two permits from Bayside City Council: one in June 2017 to remove native vegetation, with two new indigenous canopy trees required at the rear, and one in May 2018 for the two dwellings and front fence.

Beaumaris Project at a glance
LocationBeaumaris, Victoria
CouncilBayside City Council
Project typeTwo double-storey dwellings and front fence (my own development)
Planning controlsNative vegetation removal permit; two dwellings on a lot (ResCode Clause 55)
StatusVegetation permit June 2017; development permit May 2018
DesignerPhillip Mancini, Mancini Design

What were the challenges?

Beaumaris is known for its mid-century homes and coastal tree canopy, and Bayside expects new development to respect both.

Removing native vegetation on the site needed its own planning permit before the dwellings could be considered.

How did the design respond?

The vegetation permit was granted on condition that two additional indigenous canopy trees, at least 8 by 6 metres at maturity, be planted near the rear boundary.

The two homes use low, horizontal rooflines, timber accents and articulated façades that take their cue from Beaumaris's mid-century houses.

The council's conditions on the dwelling permit included separating the two homes by 2 metres at ground level and 3.57 metres upstairs, replacing one pool with landscaping, and keeping part of the front fence see-through on the corner.

What was the outcome?

Bayside City Council issued the vegetation removal permit in June 2017 and the permit for two double-storey dwellings and a front fence in May 2018.

Approvals in more detail

The site needed two separate permits. The first, in June 2017, allowed removal of native vegetation and required two new indigenous canopy trees at the rear. The second, in May 2018, approved the two dwellings and the front fence.

The vegetation permit came first because council would not look at the dwellings until the native vegetation was dealt with. On a corner site both street frontages count, so setbacks and fences had to be resolved on two sides.

This was my own development. The approvals were granted, and as at October 2026 the homes have not been built.