By Phillip Mancini, registered building practitioner · Published 16 November 2026 · Last updated 16 November 2026

Before you extend a house in Victoria, check seven things: your zone and lot size, the overlays on the property, the title, easements and services, trees, the siting rules in the Building Regulations, and which permits you need. Most of it can be checked online before you pay for design.

Not sure which of these apply to your house? Email me what you plan to build and where. The first conversation is free.

1. What do your zone and lot size decide?

Your zone and the size of your lot set the baseline. In the General Residential, Neighbourhood Residential and Housing Choice and Transport zones, a planning permit is required to construct or extend one dwelling on a lot of less than 300 m². On a lot of 300 m² or more, the zone does not require a planning permit to extend one dwelling. The siting rules are generally assessed through the building permit instead, although an overlay or another provision of the planning scheme can still require one.

On a lot under 300 m², the application may qualify for the faster VicSmart process if it meets the listed standards. The pathway is explained in do I need a planning permit to extend my house?

2. Which overlays are on the property?

An overlay can require a planning permit even when the zone does not. The Heritage Overlay requires a permit to construct a building or carry out works. The Land Subject to Inundation Overlay and the Special Building Overlay also require a permit to construct a building or carry out works, with some exceptions. Design and Development Overlays and Neighbourhood Character Overlays can set their own height, setback and design requirements.

Your VicPlan Planning Property Report shows the zone and the overlays on the property and links to the provisions, so run it first. In Port Phillip, see heritage overlay permits in St Kilda and Port Phillip.

3. What does the title say?

The certificate of title can carry restrictions that the planning scheme does not show. A restrictive covenant is a private agreement between landowners that limits the way land can be used and developed, for example by limiting development to one house on a lot or controlling the building materials used. Covenants are recorded on the title, and a title search through Landata shows whether one affects your property. A section 173 agreement sets out conditions or restrictions on the use or development of land and may also affect what you can build.

Order the title and plan of subdivision before you design, because a covenant or agreement may restrict an extension that the zone otherwise allows. A solicitor or conveyancer can advise on a specific covenant.

4. Are there easements or services in the way?

Building over an easement needs the consent of the authority that holds it. Regulation 130 of the Building Regulations 2018 requires the report and consent of the relevant service authority to a building permit application to construct a building over an easement vested in that authority. The notes to that regulation add that section 148 of the Water Act 1989 prohibits building a structure over an easement for water supply, sewerage or drainage purposes without the water authority’s consent. It also prohibits building within 5 metres of Melbourne Water’s works without that consent.

Your title plan and a survey show the easements. The water authority can tell you what it requires near sewer and stormwater lines.

5. Which trees could affect the design?

A planning permit is required to remove, destroy or lop an existing canopy tree in the Mixed Use, Township, Residential Growth, General Residential, Neighbourhood Residential and Housing Choice and Transport zones. A canopy tree is a tree at least 5 metres high with an average canopy diameter of at least 4 metres. Exemptions apply, including for a tree other than a boundary canopy tree on a site that already has a dwelling. A boundary canopy tree has part of its trunk within 6 metres of the narrowest street frontage or 4.5 metres of the rear boundary.

Other controls, such as a Vegetation Protection Overlay, may apply separately. On a lot under 300 m², the tree canopy standard in Clause 54 is also one of the VicSmart standards.

6. What do the siting rules allow?

Part 5 of the Building Regulations 2018 sets siting rules for a single dwelling. They cover street setbacks, building height, site coverage, minimum garden area, permeability, side and rear setbacks, walls and carports on boundaries, daylight to existing windows, solar access, overshadowing of neighbours’ open space, overlooking and private open space.

On a lot under 300 m², the council assesses the matching Clause 54 standards in the planning permit. Otherwise the building surveyor assesses the regulations as part of the building permit. If a design does not meet one of these rules, the council’s report and consent may be needed before the building permit can be issued. The side and rear setback calculator shows what a wall height needs.

7. Which permits do you need, and in what order?

A planning permit, where one is needed, comes from the council and must be issued before you can obtain a building permit. A building permit is needed for most building work, with limited exemptions such as some minor alterations, pergolas associated with houses and small garden sheds. A registered building surveyor assesses the application for compliance with the Building Act 1993, the Building Regulations 2018 and the National Construction Code, and issues the permit. Report and consent, water authority consent and structural engineering sit alongside these. See planning permit or building permit: which do I need? and permit timeframes and fees.

If you are buying a house to extend, the Planning, Feasibility & Risk Report is a fixed-price desktop assessment that works through these checks before you commit, and what to check before auction covers buying a unit to extend. When you are ready to design, see house extension design in Melbourne.

FAQ

How far can I extend my house in Victoria?

There is no single distance. The limit comes from the siting rules in Part 5 of the Building Regulations 2018 (or the matching Clause 54 standards on a lot under 300 square metres), from any overlay, and from your title. Street and boundary setbacks, building height, site coverage and garden area are the usual starting points. A design that does not meet one of the rules may need the council’s report and consent.

Can I add a room to my house without a permit?

Most building work needs a building permit, with limited exemptions such as some minor alterations, pergolas associated with houses and small garden sheds. A planning permit is a separate question: on a lot of 300 square metres or more the zone does not require one to extend one dwelling, although an overlay or another provision of the planning scheme can. Ask your council or a building surveyor before you assume a small addition is exempt.

Do I need a permit to remove a tree before extending?

Possibly. A planning permit is required to remove, destroy or lop an existing canopy tree in the Mixed Use, Township, Residential Growth, General Residential, Neighbourhood Residential and Housing Choice and Transport zones. Exemptions include a tree other than a boundary canopy tree on a site that already has a dwelling. Overlays can add their own tree controls. Check with your council before removing a tree.

Can a covenant stop my extension?

It may. A restrictive covenant is a private agreement between landowners that can limit how land is developed, for example to one house on a lot, and it is recorded on the title. A title search shows whether one applies. Ask a solicitor or conveyancer about a specific covenant.

Where do I check the zone and overlays on my property?

The VicPlan Planning Property Report shows the zone and the overlays that affect any property in Victoria and links to the provisions in the planning scheme. Your council’s planning team can then confirm what applies to your work.