By Phillip Mancini, registered building practitioner · Published 9 November 2026 · Last updated 9 November 2026

Council has 60 statutory days to decide a planning permit application, and that clock restarts if it asks for more information. A building surveyor has 10 business days to decide a building permit for a house once any reports and consents are in. Government fees for a single house are set by regulation and change each 1 July: in 2026-27 a planning permit for one dwelling costs $233.10 to $1,744.30, depending on the cost of the work.

How long does a planning permit take?

  • Standard applications: 60 statutory days. If council has not decided within that time, you can apply to VCAT for a review of its failure to grant a permit.
  • VicSmart applications: 10 business days. VicSmart is a faster stream for simple, listed kinds of application.
  • Further information resets the clock. If council asks for more information within the prescribed time, the time starts again from the day you give it.
  • Public notice adds time. Where neighbours must be notified, the application cannot be decided until the notice period has run.

Statutory days are not the same as calendar time since lodging. Most applications take longer than 60 days from lodgement once information requests and notice are counted. A complete, well-prepared application is the best way to keep it moving.

What does a planning permit cost?

Planning application fees are set by the state in fee units and are the same at every council. For a permit to develop or extend one dwelling, 2026-27:

Estimated cost of the developmentFee
$10,000 or less$233.10
$10,001 to $100,000$734.00
$100,001 to $500,000$1,502.50
$500,001 to $1,000,000$1,623.40
$1,000,001 to $2,000,000$1,744.30
VicSmart, estimated cost $10,000 or less$233.10
VicSmart, estimated cost over $10,000$500.80

Where the estimated cost of a development is more than $1,344,000, a Metropolitan Planning Levy is also payable to the State Revenue Office before the application can be lodged.

How long does a building permit take?

  • The building surveyor’s decision: within 10 business days for a house (Class 1) or outbuilding (Class 10), counted from when all reports and consents are received, or are due.
  • Report and consent from council, where the design departs from a siting rule: council has 15 business days to respond for a siting matter or a front fence, and 10 business days for most other matters.
  • Once the permit is issued: building work on a house must start within 12 months and be finished within 24 months. Otherwise the permit lapses.

What does a building permit cost?

Item2026-27Set by
Building surveyor’s feeQuoted by the surveyorNot regulated: ask for a written quote
Building permit levyPayable where the cost of work is over $10,000; use the Building and Plumbing Commission’s levy calculatorBuilding Act 1993
Lodgement fee to councilAbout $142 (8.23 fee units)Building Regulations 2018, reg 45
Report and consent from council, siting rules (maximum)About $474 (27.45 fee units)Building Regulations 2018, reg 36(2A)
Report and consent for demolition (maximum)About $99 (5.75 fee units)Building Regulations 2018, reg 36(1)

A fee unit is $17.27 from 1 July 2026 to 30 June 2027. The Building Reform Levy that started on 1 July 2026 applies to buildings of classes 2 to 8 costing $1.5 million or more, so not to a house or its outbuildings.

How do I keep the time down?

  1. Check the zone, overlays and title before you design, so the permits you need are known from the start.
  2. Lodge a complete planning application, so council has less reason to ask for more information.
  3. Design to the siting rules where you can, so the building permit does not need report and consent.
  4. Line up the engineer, energy rater and surveyor early, so the building permit documents are ready when the planning permit arrives.

I explain which permits a project needs in Planning Permit or Building Permit: Which Do I Need? If you would like to know which permits your project needs before you start, the Planning, Feasibility & Risk Report sets them out in order, for $495 including GST.

FAQ

How long does a planning permit take in Victoria?

Council has 60 statutory days to decide, or 10 business days for a VicSmart application. The clock restarts if council asks for more information, and public notice adds time.

How much does a planning permit cost in Victoria?

For one dwelling in 2026-27, from $233.10 for work of $10,000 or less to $1,744.30 for work of $1 million to $2 million. The fees are set by the state and change each 1 July.

How long does a building permit take?

The building surveyor has 10 business days for a house once any reports and consents are received. Report and consent from council can add 10 to 15 business days.

How much does a building permit cost?

The building surveyor sets their own fee. On top are the building permit levy (where the work costs over $10,000), a council lodgement fee of about $142, and any report and consent fees.

Sources

Fees checked November 2026. Government fees change each 1 July.