Who Pays When the Builder Misses a Detail on the Approved Drawings?
A real question from a client, and how I answered it
In Victoria, if a detail is clearly shown on the drawings in your building contract, the builder is generally responsible for building it as drawn. Missing it on site doesn’t make it an extra. The usual outcome is that the builder fixes it to match the documentation, at their own cost.
What happened?
A client building a renovation contacted me about a bathroom window. The waterproofing and the tiled finish to the window sill were documented on the working drawings. On site, the sill was finished without them. When the client raised it, the builder said nobody had told them separately, pointed to the interior designer, and suggested it would be an extra.
Why do the contract drawings take precedence?
The approved working drawings form part of your building contract and of the building permit documentation. They set out the builder’s scope of work. Under section 8 of the Domestic Building Contracts Act 1995, the builder warrants that the work will be carried out in a proper and workmanlike manner and in accordance with the plans and specifications set out in the contract.
So a detail that is on the drawings doesn’t need a separate reminder from you, your designer or your interior designer. Verbal advice, or the lack of it, doesn’t override the contract documents. The drawings speak for themselves.
Does the building code require it anyway?
For a window in a shower, often yes. The National Construction Code’s wet-area rules (Housing Provisions Part 10.2, which also draws on AS 3740, the standard for waterproofing domestic wet areas) require the walls of a shower area to be waterproof to at least 1800 mm above the floor. A window sill that sits inside the shower area, below that height, falls within the area that has to be waterproof. Your building surveyor can confirm how this applies to your particular window.
What should you do if your builder misses a documented detail?
| Step | What to do |
|---|---|
| 1. Point to the drawing | Write to the builder and quote the drawing number and detail that shows the item. |
| 2. Act before it’s covered up | Raise it as soon as you notice. Fixing waterproofing before tiling is far simpler than after. |
| 3. Keep a record | Take dated photos, and keep emails and site notes. |
| 4. Ask your designer | Your designer can confirm what the drawings require and how the detail was meant to be built. |
| 5. If you can’t agree | Domestic Building Dispute Resolution Victoria (DBDRV) offers free conciliation. You must try DBDRV before applying to VCAT. |
When does this not apply?
It applies to details that are clearly documented in the contract drawings and specifications. Changes you ask for after signing are variations and are usually charged. If a detail was never documented, the position is less clear-cut. This article is general information from a building designer, not legal advice. For a dispute about your contract, get advice on your specific situation.
How do you avoid this in the first place?
Clear, complete construction documentation is the best protection, because it leaves no room to argue about scope. If you want an independent check during the build, I offer design intent checks on request: a report documenting whether and where the build has departed from the design. They are not compliance, structural or permit inspections.
Sources: Domestic Building Contracts Act 1995 (Vic), s8; ABCB Housing Provisions Part 10.2, Wet area waterproofing; Building Victoria: Resolve disputes; a Mancini Design client enquiry (details withheld).